EAST BERGHOLT PARISH COUNCIL
PERFORMANCE SPECIFICATION
REPAIR AND RESURFACING OF TENNIS COURTS 2 & 3
Document Status and Disclaimer
This document constitutes the Performance Specification for the repair and
resurfacing of Tennis Courts 2 and 3 at East Bergholt Tennis Club. It has been prepared
to provide all tenderers with a common basis upon which to submit competitive
tenders.
The specification defines the minimum standards and performance outcomes
required by the Employer. Unless expressly stated otherwise, it does not prescribe the
Contractor’s construction methodology.
Tenderers are responsible for inspecting the Site, verifying existing conditions,
determining their own construction methodology, complying with all statutory
requirements and including within their Tender everything necessary to complete the
Works in accordance with this specification.
Submission of a Tender shall be deemed confirmation that the Tenderer has fully
satisfied themselves as to the nature and extent of the Works.
Contents
1. Introduction
2. Employer’s Requirements
3. Employer’s Design Intent
4. Performance Specification
5. Technical Requirements
6. Contractor Requirements
7. Pricing Schedule
8. Tender Submission Requirements
9. Tender Assessment and Award Criteria
1. Introduction
1.1 Employer
The Employer is East Bergholt Parish Council.
11 August 2026
2
1.2 Project
The project comprises the repair and resurfacing of Tennis Courts 2 and 3 at Gandish
Road Playing Fields, East Bergholt, including all associated preparation, repairs,
resurfacing, sports coating and line marking necessary to provide a durable, safe and
high-quality playing surface.
1.3 Procurement Objective
The Employer seeks to appoint an experienced specialist contractor to deliver a high-
quality refurbishment providing long-term value and minimal future maintenance.
1.4 Form of Tender
Tenderers shall submit a fixed price based upon these Employer’s Requirements.
Where significant structural defects are discovered that could not reasonably have
been identified during the pre-tender inspection, these shall be referred to the
Employer before additional work proceeds.
2. Employer’s Requirements
The Employer requires the successful Contractor to:
• Deliver two refurbished porous macadam tennis courts suitable for year-round
club use.
• Achieve a durable, safe and visually attractive finished facility.
• Minimise disruption to Club operations (cricket & tennis) during construction.
• Complete the Works in accordance with recognised industry good practice.
• Provide appropriate warranties and maintenance guidance.
• Work to be carried out during July and August 2027 with latest completion by
31 August 2027. This is critical to achieve the Sport England grant.
3. Employer’s Design Intent
The Employer requires the successful Tenderer to deliver two refurbished porous
macadam tennis courts that provide a safe, durable and visually attractive playing
facility suitable for year-round recreational and club tennis.
The completed works shall:
• provide a smooth, even and free-draining playing surface;
• rectify existing defects affecting playability and safety on court 3;
• extend the operational life of the courts;
• minimise future maintenance requirements;
• utilise materials appropriate for outdoor porous macadam tennis courts;
11 August 2026
3
• comply with recognised industry standards, specifically (SAPCA) and preferably
also Tennis Industry Association UK, and current good practice; and
• be completed in a manner that minimises disruption to the Club and its
members and other users of the Playing Fields including minimising noise, dust
and pollution and dispose of waste responsibly.
Except where expressly stated within this specification, the Contractor shall remain
responsible for selecting the detailed construction methodology, sequencing of
operations and materials necessary to achieve these performance requirements.
Alternative technical solutions may be proposed provided they meet or exceed the
requirements of this specification and are clearly identified as alternatives to the
compliant Tender.
4. Performance Specification
4.1 General Requirements
The Contractor shall provide all labour, supervision, plant, equipment, materials,
transport, temporary works, waste disposal and incidental items necessary to complete
the Works.
The Contractor shall inspect the Site before submitting a Tender and shall be deemed
to have satisfied themselves regarding the nature and extent of the Works.
4.2 Site Establishment
The Contractor shall:
• establish the Site safely;
• provide appropriate barriers and warning signage;
• protect adjacent property and existing infrastructure;
• maintain safe access where practicable; and
• keep the Site clean throughout the Works.
All waste shall be removed from Site and disposed of at licensed facilities.
4.3 Existing Surface Preparation
Preparation shall include:
• removal of moss, algae and biological growth;
• weed treatment where required;
• specialist pressure washing;
• removal of loose material and debris; and
• cleaning of drainage channels and outlets where provided.
11 August 2026
4
4.4 Investigation of Existing Defects
The Contractor shall inspect both courts for settlement, cracking, deformation,
movement and edge deterioration.
Significant structural defects are identified on court 3, requiring reconstruction beyond
the scope of resurfacing, the cost of this should be identified in the Tender.
Tenderers shall submit a written pre-construction condition report identifying all visible
defects and confirming the courts’ condition prior to commencement
Minor repairs shall be included within the Contract Sum.
4.5 Drainage Performance
The completed courts shall remain free-draining.
Existing drainage shall remain fully operational and any localised drainage defects
encountered during the Works shall be addressed.
A water test on completion shall demonstrate that there is no water pooling after 30
minutes.
4.6 Court Edges and Ancillary Fittings
The Contractor shall inspect and prepare perimeter edges and adjust or replace net
post sockets and centre anchors where necessary to ensure they finish flush with the
completed surface.
4.7 Resurfacing
The Contractor shall provide a new porous asphalt wearing course designed
specifically for outdoor tennis courts.
The Tender shall identify the proposed system, material specification, nominal thickness
and expected service life.
4.8 Sports Surface Coating
A proprietary sports coating suitable for porous macadam tennis courts shall be
applied following adequate curing of the resurfacing which improves durability and
increases slip resistance.
Preferred colours are as per current courts:
• Playing Area – Dark Blue
• Surround – Dark Green
Equivalent colours may be proposed for approval.
11 August 2026
5
4.9 Line Marking
White tennis court markings shall comply with current Lawn Tennis Association
requirements.
4.10 Quality of Finished Surface
The completed courts shall:
• be smooth and visually consistent;
• be free from ridges, depressions and significant undulations;
• drain freely;
• present a professional appearance suitable for club use.
4.11 Practical Completion
Practical Completion shall only occur when:
• all works are complete;
• defects have been rectified;
• the Site has been cleared;
• maintenance guidance has been issued; and
• warranty documentation has been provided.
5. Technical Requirements
5.1 General
Materials and workmanship shall be appropriate for permanent outdoor porous
macadam tennis courts and comply with recognised industry standards and good
practice.
5.2 Materials
All materials shall be:
• new;
• fit for purpose;
• supplied by recognised manufacturers; and
• installed in accordance with manufacturers’ recommendations.
Product data sheets shall be supplied upon request.
5.3 Porous Asphalt Wearing Course
The Contractor shall identify:
• asphalt specification;
11 August 2026
6
• nominal thickness;
• design life;
• curing period.
The finished surface shall be uniform and free from visible defects.
5.4 Surface Regularity
The finished courts shall provide a smooth and even playing surface free from ridges,
depressions, abrupt level changes or trip hazards.
5.5 Drainage Performance
The courts shall remain free-draining with no persistent ponding resulting from
defective workmanship.
A water test on completion shall demonstrate that there is no water pooling after 30
minutes.
5.6 Court Fittings
Net post sockets and centre anchors shall be securely fixed, correctly aligned and
finish flush with the playing surface.
5.7 Sports Surface Coating
The coating shall provide:
• a uniform finish;
• UV resistance;
• appropriate slip resistance;
• long-term durability.
5.8 Colour Scheme
Area Colour
Playing Area Dark Blue
Surround Dark Green
Line Markings White
5.9 Line Marking
All line markings shall comply with current LTA dimensions and be accurately set out.
5.10 Workmanship
All workmanship shall be undertaken by suitably experienced personnel.
The Employer reserves the right to reject workmanship considered unsatisfactory.
11 August 2026
7
5.11 Inspection and Quality Assurance
The Employer may inspect the Works at any reasonable time.
Inspection shall not relieve the Contractor of responsibility for quality.
5.12 Defects Liability
The Contractor shall rectify defects arising from defective workmanship or materials
during a minimum 12-month Defects Liability Period.
6. Contractor Requirements
6.1 General
The Employer intends to appoint a specialist contractor experienced in resurfacing
outdoor porous macadam tennis courts.
6.2 Site Inspection
Tenderers shall inspect the Site before submitting a Tender.
Submission of a Tender confirms that the Tenderer has satisfied themselves regarding:
• site conditions;
• access;
• working constraints; and
• the extent of the Works.
6.3 Experience
Tenderers shall provide details of at least two comparable projects completed within
the previous five years.
6.4 Personnel
Tenderers shall identify the proposed Project Manager and Site Supervisor.
6.5 Programme
Tenderers shall submit a proposed Construction Phased Plan/programme showing
commencement, sequence of key activities, curing periods and anticipated
completion including a weather contingency plan.
6.6 Health and Safety
The Contractor shall comply with all applicable health and safety legislation and will
provide confirmation of competency, site specific risk assessments and method
statements.
11 August 2026
8
6.7 Social Value
The Client seeks to maximise social value arising from this project. Tenderers shall
provide a short statement describing how their delivery of the Works will contribute to
social, economic and environmental wellbeing within East Bergholt
6.8 Insurance
The Contractor shall maintain:
• Public Liability Insurance – minimum £10 million.
• Employers’ Liability Insurance – minimum £10 million.
Evidence shall be provided before commencement.
6.9 Quality Assurance
The Contractor shall implement suitable quality assurance procedures throughout the
Works.
6.10 Post Completion and Warranty
The Contractor shall provide a post-completion defects inspection with the Playing
Fields Committee at around 6 months, with a requirement to rectify defects within 20
days. The Playing Fields Committee shall organize this with the Contractor.
The Contractor shall provide a minimum 36-month workmanship warranty together
with manufacturers’ warranties where available.
6.11 Maintenance Guidance
At handover the Contractor shall provide written maintenance recommendations for
routine care of the courts, as-built drawing, warranties, product data sheets, and
photographic record of works.
7. Pricing Schedule
Tenderers shall complete the following Pricing Schedule.
Item Tender Price (£ excluding VAT)
Site establishment
Surface preparation (weed/moss treatment)
Minor repairs
Edge preparation
Court 3 bump investigation & repair
Court fittings
Porous asphalt resurfacing
11 August 2026
9
Item Tender Price (£ excluding VAT)
Sport surface coating
Tennis line marking
Site clearance and handover
Total Tender Sum (excluding VAT)
VAT
Total Tender Sum (including VAT)
Provisional Sums
Any proposed provisional sums shall be separately identified for:
• significant structural reconstruction;
• replacement of failed sub-base;
• additional drainage works.
No provisional sum shall be expended without the Employer’s written approval.
8. Tender Submission Requirements
8.1 General
Tenderers shall submit a complete Tender based upon these Employer’s Requirements.
The Tender shall remain valid for 6 months from the Tender Return Date.
The Employer reserves the right not to accept the lowest, or any, Tender received.
8.2 Tender Submission
Tenderers shall submit:
• Completed Pricing Schedule.
• Proposed construction phase plan/programme.
• Details of the proposed resurfacing system.
• Details of any proposed alternative solutions.
• Details of at least two comparable projects.
• Details of the proposed Project Manager and Site Supervisor.
• Copies of current insurance certificates.
• Confirmation of warranty provisions.
• Confirmation that a site inspection has been undertaken.
Incomplete submissions may be excluded from further consideration.
11 August 2026
10
8.3 Tender Queries
Requests for clarification shall be submitted in writing or by phoning and speaking to
Graham White, Treasurer East Bergholt Parish Council, before the Tender Return Date.
8.4 Acceptance
Acceptance of a Tender shall not create a binding contract until confirmed in writing
by the Employer.
The Employer reserves the right to seek clarification, negotiate with the preferred
Tenderer or abandon the procurement process without liability.
9. Tender Assessment and Award Criteria
9.1 Evaluation Process
Tenders will be evaluated using the Most Economically Advantageous Tender (MEAT)
approach, considering both quality and price.
9.2 Assessment Criteria
Criterion Weighting
Technical compliance with the Employer’s Requirements 35%
Relevant experience and references 20%
Programme and methodology 15%
Warranty and aftercare 10%
Tender price 20%
9.3 Assessment
The evaluation will consider:
• compliance with this specification;
• proposed resurfacing system;
• relevant experience;
• Construction plan/programme;
• project management arrangements;
• warranty and maintenance proposals;
• overall value for money.
The Employer may seek clarification of any aspect of a Tender where appropriate.
9.4 Contract Award
The Contract is intended to be awarded to the Tenderer offering the best overall
value based upon the published assessment criteria.
11 August 2026
11
The Employer reserves the right not to award a Contract if no Tender is considered to
provide satisfactory value or compliance with these Employer’s Requirements.